sync brain updates and archive recent notes
This commit is contained in:
@@ -0,0 +1,83 @@
|
||||
---
|
||||
Date: 2026-04-30
|
||||
Author: Adolfo Reyna
|
||||
Tags: #project #220emerald #church #hosting #facilities #ac
|
||||
---
|
||||
|
||||
# 220 Emerald Church Hosting Preparation 2026
|
||||
|
||||
## Objective
|
||||
Prepare the 220 Emerald property to host church events by aligning with the Elders on support needs and executing facility improvements for:
|
||||
- Main house church room
|
||||
- Barn gathering area
|
||||
|
||||
## Current Priorities
|
||||
- [ ] Meet with Elders to confirm vision, expected attendance, and support model.
|
||||
- [ ] Define scope and budget for AC in:
|
||||
- [ ] Main house church room
|
||||
- [ ] Barn
|
||||
- [ ] Build phased plan for barn upgrades:
|
||||
- [ ] Carpet/flooring requirements
|
||||
- [ ] Potential window additions
|
||||
- [ ] Bathroom feasibility (plumbing, permits, cost)
|
||||
|
||||
## Workstreams
|
||||
|
||||
### 1) Elder Alignment & Ministry Support
|
||||
- [ ] Confirm desired launch timeline for hosting events.
|
||||
- [ ] Clarify church support (financial, volunteer labor, materials, technical).
|
||||
- [ ] Agree on ministry use-cases (prayer nights, classes, youth, worship, meals).
|
||||
- [ ] Identify point person(s) for recurring coordination.
|
||||
|
||||
### 2) AC Planning & Execution
|
||||
- [ ] Request at least 2–3 quotes for main house room AC options.
|
||||
- [ ] Request at least 2–3 quotes for barn AC options.
|
||||
- [ ] Evaluate load sizing, insulation impact, and electrical readiness.
|
||||
- [ ] Select vendor and schedule install windows.
|
||||
|
||||
### 3) Barn Buildout Discovery
|
||||
- [ ] Carpet: material options, durability, and cleanability.
|
||||
- [ ] Windows: daylight/ventilation goals + placement options.
|
||||
- [ ] Bathrooms: number needed, plumbing route, septic/sewer implications, permit path.
|
||||
- [ ] Produce rough order-of-magnitude budget and implementation phases.
|
||||
|
||||
## Suggested Phases
|
||||
- **Phase 1 (Immediate):** Elder alignment + AC scoping + rough budget.
|
||||
- **Phase 2 (Short Term):** AC installation in priority spaces.
|
||||
- **Phase 3 (Mid Term):** Barn interior improvements (carpet/windows).
|
||||
- **Phase 4 (Longer Term):** Bathroom project execution.
|
||||
|
||||
## Key Open Questions
|
||||
- [ ] Target date for first church event at 220 Emerald?
|
||||
- [ ] Typical and max attendance?
|
||||
- [ ] Available church budget or reimbursement model?
|
||||
- [ ] Permit constraints for barn modifications and bathrooms?
|
||||
|
||||
## Next Action
|
||||
- [ ] Send Elder outreach email and request planning meeting.
|
||||
|
||||
## Utility Cost Tracking (FPL) — Guest/Little House
|
||||
- **Account:** 42066-68446
|
||||
- **Source:** Local Thunderbird email bills (`FPL_Email_Bill@billing.fpl.com`)
|
||||
- **Period tracked:** 2025-09 to 2026-05
|
||||
|
||||
### Monthly Bills
|
||||
- 2025-09: $51.23
|
||||
- 2025-10: $85.96
|
||||
- 2025-11: $59.38
|
||||
- 2025-12: $75.53
|
||||
- 2026-01: $52.37
|
||||
- 2026-02: $51.19
|
||||
- 2026-03: $49.60
|
||||
- 2026-04: $60.83
|
||||
- 2026-05: $82.47
|
||||
|
||||
### Snapshot Analysis
|
||||
- **Total (9 months):** $568.56
|
||||
- **Average / month:** $63.17
|
||||
- **Min:** $49.60 (2026-03)
|
||||
- **Max:** $85.96 (2025-10)
|
||||
- **Trend note:** Lowest in Jan–Mar; increased in Apr–May, likely seasonal cooling load.
|
||||
|
||||
---
|
||||
[[Projects]] | [[Index]] | [[areas/maintenance/220_emerald]]
|
||||